The Civil Engineering and Development
Department HKSAR has appointed MateriaLab Consultants Limited (MCL) to
undertake the Environmental Team services for the Project and implement the
EM&A works.
ii.
This Monthly EM&A report presents the environmental
monitoring and audit works for the period between 1 February and 28 February
2021. As informed by the Contractor, no major construction activities were
carried out in the reporting month.
Breaches of the Action and Limit Levels
iii. An Action Level exceedance for 24-hr TSP
were recorded in the reporting month. An exceedance were recorded at KTD2c on 1
February 2021.
iv. No Action / Limit Level exceedance was
recorded for 24-hr TSP at KTD1 and KER1 in the reporting month.
v. No Action / Limit Level exceedance was
recorded for construction noise at KTD1, KTD2c and KER1 in the reporting month.
Complaint, Notification of Summons and Successful Prosecution
vi. No environmental complaint, notification of
summons and successful prosecution were received in the reporting month.
Reporting Changes
vii. There was no reporting change in the
reporting month.
Future Key Issues
viii. There was no future key issues in the
reporting month.